Current construction

Find and learn about construction happening now for Green Line. Narrow down your search results by using filters or view construction impacts and notices to see what type of work is being done in your area. 

Viewing 5 articles.

Impacts and notices

Find out what areas are impacted by Green Line construction and the type of work being done.

Last updated: June 12, 2024

Downtown

To make way for the Green Line stations and tunnel under 2 Street S.W., work is underway to move underground utilities (e.g., Telus, ENMAX) away from 2 Street and into adjacent streets and avenues.


Location Project type Impact Status End date Details
2 Street SW south of the Bow River Pathway ENMAX Utility Relocation
  • Pedestrian detours
  • Lane Closures
  • No on-street parking

June 2024

See ENMAX site

Beltline East

To make way for the Green Line station and tunnel under 11 Avenue S.E., we are moving underground utilities (storm water and sanitary) into 12 Avenue S.E.


Location Project type Impact Status End date Details

6 Street S.E. between 11 and 12 Avenues

City of Calgary Utility Relocation 

  • Pedestrian detours
  • Full road closures
  • Removal of on-street parking

June 2024

See the detailed detour and construction map

3 Street S.E., 11 Avenue, 12 Avenue

ENMAX Utility Transmission

  • Pedestrian detours
  • Cycle track detours
  • Lane closures
  • Removal of on-street parking

June 2024

See ENMAX site

12 Avenue and 6 Street S.E.

City of Calgary Utility Relocation

  • Pedestrian detours
  • Lane Closures
  • Removal of on-street parking

June 2024

See the detailed detour and construction map

South side of 11 Avenue, between 5 and 5 Street S.E. 

Buildings Demolition

  • Noise and dust
  • Increased truck traffic
  • Occasional parking land closure

End of June 2024

See the detailed detour and construction map

Beltline West

To make way for the Green Line station and tunnel under 11 Avenue S.W., we are relocating and realigning existing third-party utilities away from 11 Avenue S.W. into adjacent streets, avenues and alleyways.


Ogden

Ogden

Work is planned for this area to make way for the future Ogden station.


Location Project type Impact Status End date Details

78 Avenue S.E. from 25 Street S.E. to 27 Street S.E. and Ogden Dale Road S.E.

Phased closures for road upgrades
  • Sidewalk closures
  • Partial lane closures
  • Congestion and traffic delays 
  • Construction noise

April 2024 - September 2024

See the detailed construction map

Ogden Dale Road S.E. upgrades

Green Line roadworks
  • Lane closures
  • Congestion and traffic delays 
  • Construction noise

May 15, 2024 - September 2024

See the detailed construction map

78 Avenue S.E.

Secant pile wall
  • Heavy vehicle traffic
  • Parking removal
  • Speed restriction
  • Noise
  • Vibrations

End of year 2024

See the detailed construction map

78 Avenue S.E.

Near 72 Avenue S.E.

69 Avenue. S.E

78 Avenue S.E. vehicle tunnel and a pedestrian tunnel near 72 Avenue S.E.
  • Noise 
  • Lane restrictions
  • Restriction for walking/ wheeling 
  • Heavy machinery operating in the area

Estimated to be completed by summer 2025

See the 78 Avenue Project page