Bridgeland Edmonton Trail N.E. Main Street

Bridgeland Main Streets

Phase 1 – Edmonton Trail N.E.

Project update - May 2023

Phase one of the Bridgeland Main Street, between Memorial Drive and 2 Avenue N.E., has started the second season of construction. Work locations are listed in the chart below.

  • Starting the week of April 17:
    • Westbound Memorial Drive at Edmonton Trail
  • Starting in May:
    • East side of Edmonton Trail between 2 Ave. and 3 Ave. N.E.
    • East side of Edmonton Trail between Memorial Dr. and Meredith Rd. N.E.
    • West side of 4 St. N.E. between 2 Ave. and 3 Ave. N.E.

Phase two of the Bridgeland Main Street project has received the necessary funding for construction. We expect construction to start in the Summer of 2023. We are currently preparing to hire and onboard a contractor and once hired we will be able to provide more information on the schedule and sequencing of the anticipated construction.

Contact us

Do you have a specific question about the Bridgeland Main Street Construction project? You can send us an email: bridgelandmainstreet@calgary.ca

Stay connected

Sign up for our email updates to receive ongoing updates about the Bridgeland Street Main Street construction project.

Work locations and construction impacts

Location Project type Impact Status Anticipated Schedule* More Information

Westbound Memorial Drive at Edmonton Trail

  • Wider sidewalks
  • Changes to the driveway
  • Curb repair
  • Improvements to the wheeling lane
  • Tree planting
  • Noise
  • Lane restrictions
  • Restriction for walking/ wheeling 
  • Heavy machinery operating in the area

Begins April 2023

April 17 (4-6 weeks of construction)

Construction notice

East side of Edmonton Trail between 2 Ave. and 3 Ave. N.E.

  • Wider sidewalks
  • Curb repair
  • Improvements to the wheeling lane
  • Tree planting
  • Noise
  • Lane restrictions
  • Restriction for walking/ wheeling 
  • Heavy machinery operating in the area

Begins May 2023

May 8 (8-10 weeks of construction)

Construction notice

East side of Edmonton Trail between Memorial Dr. and Meredith Rd. N.E.

  • Wider sidewalks
  • Curb repair
  • Tree planting
  • Noise
  • Lane restrictions
  • Restriction for walking/ wheeling 
  • Heavy machinery operating in the area

Begins May 2023

May 15 (12-14 weeks of construction)

Construction notice

West side of 4 St N.E. between 2 Ave and 3 Ave N.E.

  • Wider sidewalks
  • Curb repair
  • Improvements to the wheeling lane
  • Tree planting
  • Noise
  • Lane restrictions
  • Restriction for walking/ wheeling 
  • Heavy machinery operating in the area

Begins May 2023

May 17 (8-10 weeks of construction)

Construction notice

* Please note: the anticipated schedule is subject to change depending on factors such as complexity, weather, supply chain, and access.

What to expect for Phase 1

We expect Phase One of the Bridgeland Main Street to be complete in 2023. Phase one includes streetscape improvements and infrastructure upgrades along Edmonton Tr from Memorial Drive to 2 Avenue N.E. as well as Gateway features on Memorial Drive beneath the 4 Ave flyover and at the triangle where 4 Street meets Edmonton Trai.

The map below shows the completed work in orange and the 2023 work in green.

Click to enlarge map

Project scope

The Edmonton Trail N.E. Main Street underwent the “design” step of the Main Streets program between 2018 and 2021. Based on citizen and interest holder feedback, technical analysis, and financial considerations, the plan supports the needs identified by the community.

  • A focus on urban design and placemaking.
  • Enhanced pedestrian safety and comfort.
  • Improved mobility options, including transit and cycling
  • ·A design that is uniquely “Bridgeland-Riverside” and reflects its heritage and community identity.
  • Improved connections to park spaces and amenities.
  • Enhancing the community’s Main Street as a destination that will support existing and new local businesses.

What will Edmonton Trail NE look like?

Along Edmonton Trail N.E. there will be:

  • Widened sidewalks
  • More plants and trees
  • New street lighting along the road and sidewalks
  • New crosswalks with wheelchair ramps complete with tactile plates to help those with vision loss at intersections
  • New waste & recycling bins, bike racks and benches
  • Southbound 4 Street between 3 and 2 Avenue N.E. will be reduced from three to two lanes
  • The separated wheeling lane will extend to 4 Street N.E. and connect to the 2 Avenue on-street bike lane
  • Extensive planting and creation of a small pocket park space within the triangle at 4 Street, with a better crossing at 2 Avenue N.E.

At the Memorial Drive Gateway there will be:

  • Reduction of parking stalls on City property
  • Re-configured Memorial Drive access to the parking lot for safety
  • Southern 4 Street access changed to an “in-only”
  • Maintained access off of Edmonton Trail
  • Larger pedestrian space and improved pedestrian connections
  • New bioretention area– a vegetated area to capture and treat stormwater
  • Improved lighting for people walking

What you can expect during construction

  • An increase in on-site construction activity, including construction crews, vehicles and heavy equipment, including an increase in noise and vibration throughout construction.
  • Sidewalk closures and detours ensure pedestrians and cyclists can travel safely through the area and still access their destinations.
  • The temporary removal of some parking, road closures and potential road detours. Traffic will be maintained during construction, except for occasional closures with a detour. 
  • Potential construction activity on weekends, weekdays, and overnight as required. 
  • We will work directly with individual businesses to provide continued access to their property as much as possible.
  • While we don't expect any major utility shutdowns, you will be notified if the need arises.
  • Temporary transit stop relocations if required.

Please note, construction in an older community like this means that sometimes we run into surprises during construction. We don't anticipate any issues, but the timeline could be impacted should we discover any surprises. 

We appreciate your patience when crews are working in the area. We know that construction impacts can be disruptive, and we will work to mitigate impacts as best we can.

Timeline

  • Live (2023)
    • Ongoing investment in development
    • Operations and maintenance
  • Build (2022 – 2023)
    • Phase 1 (Edmonton Trail)
    • Construction of designs -based on Streetscape Master Plan
  • Design (2018 – 2021)
    • Community Engagement on Bridgeland Master Plan
    • Pedestrian safety measures implemented
    • Bridgeland Streetscape Master Plan completed and approved
    • Detailed design work completed
  • Plan (2017)
    •  Land use redesignation and infrastructure assessment
  • Strategize (2014 – 2016)
    • Public engagement and market studies
    • Implementation Plan

Want to learn more about the Main Streets Program visit Calgary.ca/mainStreets


Project documents

Project background

The City has developed a Streetscape Master Plan for Bridgeland based on citizen feedback, technical analysis, and financial considerations.

The vision for the Bridgeland Main Streets project is to build a streetscape that includes well-designed, quality public realm elements and public space, that prioritize the pedestrian experience and will support ongoing redevelopment and a thriving economic environment. Once complete, it will offer a variety of safe, accessible mobility connections, new community gathering spaces, and a uniquely Bridgeland character.

The key features of Bridgeland Main Streets are:

  1. Prioritize pedestrian safety
  2. Enhanced landscaping for pedestrian comfort
  3. Unique streetscape elements
  4. New opportunities for community gathering
  5. Improved mobility options

Main Streets


The Main Streets Program is one of the ways that the City of Calgary is working to make our city “a great place to make a living, and a great place to make a life.” Our program shares The City’s common purpose of “making life better every day” by implementing a comprehensive process to transform our main streets into places where people want to live, work and play.

To reach their full potential, Calgary’s Main Streets need both public and private investment. The Main Streets program is a continuum that goes from changes to land use that will support development opportunities to a streetscape master plan that is designed to support these changes and can be constructed in a coordinated fashion. The increase in development activity will bring more people and new jobs to the community, making the area more attractive to local businesses and residents.

Core values

Main Streets are resilient, adaptable, and attractive places that support:

  • Character & Identity
    Create a street that establishes a unique sense of place and offers memorable experiences for both residents and visitors. 
  • Social & Healthy lifestyle
    Create a family-friendly and safe street environment that focuses on promoting sense of community. 
  • Mobility & Functionality
    Achieve a balance of multi-modal transportation options with a focus on friendly and inclusive design. 
  • Economic vitality
    Street improvements promote economic vitality by encouraging redevelopment opportunities and promoting investment.

This information has no legal status and cannot be used as an official interpretation of the various bylaws, codes and regulations currently in effect. The City of Calgary accepts no responsibility to persons relying solely on this information. Web pages are updated periodically. ​