The target timeline for a detailed multi-disciplinary response to a development permit application is either 35 days from receipt of a complete application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a detailed multi-disciplinary response to a development permit application is either 35 days from receipt of a complete application or based on a custom timeline created in collaboration with the applicant.
/content/dam/www/pda/pd/publishingimages/cac/metrics/dp-multi-disciplinary-decisions.jpg
The target timeline for a decision on a multi-disciplinary development permit application is either 120 days from receipt of application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a decision on a multi-disciplinary development permit application is either 120 days from receipt of application or based on a custom timeline created in collaboration with the applicant.
/content/dam/www/pda/pd/publishingimages/cac/metrics/loc-dtr.jpg
The target timeline for a detailed multi-disciplinary response to a Land Use Amendment application is either 49 days from receipt of a complete application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a detailed multi-disciplinary response to a Land Use Amendment application is either 49 days from receipt of a complete application or based on a custom timeline created in collaboration with the applicant.
/content/dam/www/pda/pd/publishingimages/cac/metrics/loc-decisions.jpg
The target timeline for a decision on a Land Use Amendment is either 180 days from receipt of application or based on a custom timeline created in collaboration with the applicant.
The target timeline for a decision on a Land Use Amendment is either 180 days from receipt of application or based on a custom timeline created in collaboration with the applicant.